This guide treats “calculate working days between two dates excel” the way busy spreadsheet users actually want it: answer first, a live tool to prove it on your own data, then the reasoning. It is written for Excel but calls out every place Google Sheets differs, and the platform toggle at the top switches all shortcuts between Windows and Mac so nothing here assumes the keyboard you are not on.

Exact answer

In Excel: use =NETWORKDAYS(start_date, end_date, [holidays]) — it counts the whole working days (Monday to Friday) between two dates, excluding weekends and any holidays you list.

Syntax

=NETWORKDAYS(start_date, end_date, [holidays])

Arguments

ArgumentDescription
start_daterequiredThe first date of the period, counted as day one.
end_daterequiredThe last date of the period; it is included in the count.
holidaysoptionalA range of dates to exclude as well, such as public holidays.

Related functions

DATEDIFWEEKDAY
ƒxWorkday CalculatorLive
Workdays
62

86 calendar days

=NETWORKDAYS(A2,B2)
Saturdays and Sundays are skipped; public holidays are not.
Ctrl+CthenCtrl+Shift+V+Cthen+Ctrl+VPaste values · WindowsMac

Need it as an auditable file?

Ships inside the linked template — formula-driven, unlocked, audit-ready.

View template

What this does

NETWORKDAYS counts whole working days between two dates. It includes both the start and end date, automatically skips every Saturday and Sunday, and skips any dates you pass in the optional holidays range as well. It is the standard way to work out delivery times, project durations or how many billable days fall in a period. If your week does not run Monday to Friday — say a Sunday-to-Thursday week — use NETWORKDAYS.INTL, which adds a weekend-pattern argument so you can define which days count as the weekend. Most people learn this as a sequence of clicks and forget it by next week; learning it as a pattern instead is what lets you apply it to the next, slightly different version of the problem without starting from scratch. That is the difference this page is trying to make. For “calculate working days between two dates excel”, the reliable version is a short checking loop, not just the first command that appears to work. Run it on a deliberately small range first, watch how the affected cells change, and only then apply the same setup to the full sheet. When a formula is involved, keep the inputs labelled beside it, reference cells instead of typing values, and apply number formatting only after the result checks out. That is what makes a calculation you can defend to a CFO or an auditor useful in real work: repeatable, auditable, and not dependent on memory or luck.

A worked example

A task starts on 01/06/2026 (a Monday) in A2 and is due 12/06/2026 (a Friday) in B2. =NETWORKDAYS(A2, B2) returns 10 — the two full weeks of weekdays, with the weekend of the 6th and 7th excluded. If 05/06/2026 is a public holiday listed in D2, then =NETWORKDAYS(A2, B2, D2) returns 9, dropping that one day too. NETWORKDAYS is the right tool for SLAs, project timelines and billing, where only Monday-to-Friday working days count and weekends and holidays must drop out automatically. If there is any chance you will reuse this, drop it into a small template tab right now: a labelled input area on the left and the formula beside it, checked once against the tool above. Next time the same question comes up, the answer is a single paste away instead of a rebuild from memory.

In Google Sheets

Everything above works in Google Sheets too. Excel and Sheets share the formula syntax used here; only the surrounding menus are arranged differently. That portability is deliberate — learn it once and it follows you between the two tools and across Windows and Mac. The aim was to get you unstuck fast and leave you a little more capable than a copy-paste would. The answer is at the top, the tool proves it, and the detail above shows why it holds — so the next time a colleague asks, you can answer without reaching for search. Treat “calculate working days between two dates excel” as a small building block rather than a chore. Once the inputs sit in their own cells and the formula reads from them, the same setup answers a dozen related questions with a tweak, and Excel keeps every dependent figure current as the data changes. The tool above is there so you can rehearse and verify before committing anything to a real workbook; the steps and worked example are there so the logic sticks. Get it right once and it stops costing you time — it starts saving it, every time the question comes back around.

Common mistakes

  • Expecting the result to exclude the start date — NETWORKDAYS counts both endpoints, so a Monday-to-Friday span is 5, not 4.
  • Leaving holidays out and over-counting across public holidays; pass a holiday range as the third argument to drop them.
  • Using NETWORKDAYS for a non-Monday-to-Friday week — it always treats Saturday and Sunday as the weekend, so use NETWORKDAYS.INTL for other patterns.

Frequently asked questions

Does NETWORKDAYS include the start and end dates?

Yes, both are counted if they fall on a weekday. A period from Monday to Friday returns 5 because every day in the inclusive range is a working day.

How do I exclude public holidays?

List the holiday dates in a column and pass that range as the third argument: =NETWORKDAYS(A2, B2, D2:D10). Any of those dates that fall on a weekday are removed from the count.

How do I count working days with a different weekend?

Use NETWORKDAYS.INTL, which takes a weekend argument — a code or a 7-character pattern — so you can define, for example, a Friday/Saturday weekend instead of Saturday/Sunday.